The Stage Sub-Score Is Two Numbers, Not a Development Label
"Under construction" sounds like a fact. It is actually a classification call, and the call can be wrong in either direction without anyone lying. MAS-Score's Stage sub-score — 10% of the total weight — reduces a project's development status to two numbers: a base score from a six-step NI 43-101-aligned ladder, and a premium that pays out only when the next step is close. A press release that says "construction has begun" and a filing that says the construction-investment decision is still pending are not describing the same classification, and the two numbers treat that distinction very differently from how a headline does.
The first number: a six-step ladder, unevenly spaced
The base score follows the stage vocabulary built into NI 43-101 disclosure practice: exploration scores 15, preliminary economic assessment (PEA) 30, pre-feasibility 45, feasibility 60, construction 75, production 95. Five of those six steps are spaced exactly 15 points apart. The sixth — construction to production — is worth 20. That is not a rounding artifact; it is the model crediting first production as disproportionately de-risking relative to every earlier transition, because every stage before it still carries execution risk that production has, by definition, already cleared. A project that moves from feasibility to construction gains the same 15 points a PEA-stage project gains by advancing to pre-feasibility — but the jump from breaking ground to pouring first metal is worth more than any single step that came before it.
Why PEA and pre-feasibility aren't just "less finished" versions of the same study
The ladder isn't an arbitrary house ranking — it tracks a real regulatory line. Under the CIM Definition Standards for Mineral Resources and Mineral Reserves, adopted by CIM Council on May 10, 2014 and incorporated by reference into NI 43-101 (the instrument currently in force, effective June 9, 2023), Inferred Mineral Resources must not be included in the economic analysis, production schedule, or estimated mine life of a publicly disclosed pre-feasibility or feasibility study[^1][^2]. A PEA carries no such restriction — it is explicitly allowed to rely on Inferred Resources, which is exactly why it sits below pre-feasibility on the ladder rather than being treated as an earlier draft of the same thing. A company that reports a PEA with a large contained-ounce figure built substantially on Inferred Resources is not withholding a more rigorous study; the regulation does not let it produce one yet, and the Stage sub-score's 15-point gap between PEA and pre-feasibility is pricing that exact constraint.
The second number: proximity only counts inside twelve months
The base score is then adjusted by a transition premium: +10 if the next stage is six months or less away, +5 if it is twelve months or less away, and zero beyond that. The design choice is deliberate — a company's own guidance about a transition three or five years out is treated as optionality, not as de-risking, because too much can still change in the intervening years for the market to price it as near-certain. This is where the two numbers can diverge sharply from a one-line label. A project described in its own materials as "under construction" with a production date still years away scores the construction base of 75 with no premium attached — the same premium-free treatment a project would get if production were a decade away rather than three years. The label says de-risking is underway; the second number says the market shouldn't yet treat the timing as settled.
A worked read: Stibnite Gold Project
Perpetua Resources' Stibnite Gold Project in Valley County, Idaho, is a useful case precisely because its own disclosures don't resolve to one clean label. The governing technical report — "Stibnite Gold Project, Feasibility Study Technical Report, Valley County, Idaho" (M3-PN170045), prepared by M3 Engineering & Technology Corp. under NI 43-101 — carries an effective date of December 22, 2020 and was filed on SEDAR on January 28, 2021[^3]: a feasibility-level study, base score 60. By the company's August 31, 2026 construction update, early physical works — including autoclave fabrication and the Burntlog Route access road — had been underway since October 21, 2025, following the receipt of required federal and state notices, and the company reaffirmed a 2029 target for the start of operations[^4]. Those two facts pull in opposite directions on a single-label reading: "feasibility study, 2021" says 60; "construction underway, 2026" says 75. Applying the Stage sub-score's own logic resolves it without needing to pick a side rhetorically — early physical works underway is the operative fact for the base score, giving 75, while a 2029 target as of a 2026 update puts the next transition roughly three years out, well outside the twelve -month window, so the premium is zero either way. The two-number read is 75 + 0. A reader relying on the word "construction" alone would have no way to know that the premium component contributes nothing here — or that it would contribute the same nothing if operations were ten years away instead of three.
The gap to the next step up is also worth sitting with. A project already in production — Lundin Gold's Fruta del Norte, covered elsewhere on this blog, is the example on hand — scores 95 on this same axis. The distance from Stibnite's 75 to that 95 is the single largest step on the entire ladder, twenty points, not fifteen. Construction is the closest a project gets to production without having cleared it, and the model treats that last gap as the biggest one on the board.
What this means for coverage
None of this is a claim that Stibnite carries a live MAS-Score on Mineralis today — it is an illustration of the Stage sub-score's mechanics applied to public disclosures from a single company. It does point at a general coverage risk: the technical report that anchors a project's classification is often years older than the press release that reports its current status, as this blog has noted before in Stibnite's own case. A 2020-effective feasibility study and a 2026 construction update are both real, current documents — neither has expired — but they answer different questions, and a Stage sub-score built only from the newer one would miss the regulatory reasoning the older one encodes. The same applies to the broader PEA/pre-feasibility/feasibility distinction this blog covered when it looked at Qualified Person sign-off: the Stage sub-score is only as reliable as the citation trail behind the stage label a company currently claims, and one Idaho gold-antimony project under Canadian NI 43-101 rules is one worked example, not a claim about how every construction-stage junior will resolve.
References
- Canadian Securities Administrators / British Columbia Securities Commission, National Instrument 43-101 — Standards of Disclosure for Mineral Projects, version currently in force, published July 25, 2023, effective June 9, 2023. Scope: Canadian securities regulation defining the PEA, pre-feasibility, and feasibility study categories and the Qualified Person framework that the Stage sub-score's ladder is aligned to.
- Canadian Institute of Mining, Metallurgy and Petroleum (CIM), "CIM Definition Standards for Mineral Resources and Mineral Reserves," adopted by CIM Council, May 10, 2014. Incorporated by reference into National Instrument 43-101. Scope: Canadian standard; the clause restricting Inferred Mineral Resources from pre-feasibility and feasibility economic analysis; no newer edition identified as of this writing.
- M3 Engineering & Technology Corp., prepared for Perpetua Resources Corp. (then Midas Gold Corp.), "Stibnite Gold Project, Feasibility Study Technical Report, Valley County, Idaho" (M3-PN170045), effective date December 22, 2020, filed on SEDAR January 28, 2021. Scope: a single project (Stibnite, Idaho); NI 43-101 feasibility-level technical report, now approaching six years old relative to this post's publication date.
- Perpetua Resources Corp., "Perpetua Resources Provides Construction Update on the Stibnite Gold Project and Exploration Activities," press release, August 31, 2026. Scope: a single company and project; describes early construction works underway since October 21, 2025 and reaffirms a 2029 operations target as of the release date — not a claim that a full construction-investment decision had been finalized as of that date.